Cleveland Hopkins International Airport Ticketing Lobby Improvements

Cleveland, Ohio

Aviation Construction

Ticketing Lobby Improvements at CLE Airport

Cleveland Construction served as the general contractor to the City of Cleveland for the interior ticket lobby rehabilitation at Cleveland Hopkins International (CLE) Airport located in Cleveland, Ohio. The project’s interior improvements included 30,000 SF of renovations to the Upper-Level Ticket Counter area, Security Checkpoint B, and the Lower Level Baggage Claim area. Goals of the project included improving the ticketing hall’s operational performance and enhancing the overall passenger experience. 

The scope of work for the Upper-Level Ticket Counter area included replacing eight existing electronic sliding glass entrance doors with six three-sleeved revolving doors to greatly reduce temperature fluctuations in the ticketing area.  Other improvements to this area included the addition of a large glass curtain wall to provide daytime light in the ticketing hall; the replacement of interior lighting with sensor-controlled LED lighting to improve energy usage; and the installation of new HVAC, fire suppression, and fire alarm systems for code compliance and public safety. Additionally, the ceiling was raised by 4 feet and the old drywall was replaced with a linear metal ceiling to reduce long-term maintenance and provide a modern look.

Security Checkpoint B improvements included the demolition of the existing public restrooms and stair approach from ticketing to the Security Checkpoint; construction of new public restrooms at the Ticketing Level; and construction of a ramp and stair approach from Ticketing to the Security Checkpoint. Improvements in the Lower-Level Baggage Claim area included aluminum composite paneled ceilings, a metal curtain wall system, aesthetically pleasing column wraps, terrazzo flooring, and new LED lighting.  Also, 14 newer-technology sliding glass exit doors were installed in the area’s seven vestibules. 

Performing demolition and renovation work within an occupied facility that has an extremely high volume of public foot traffic presented a unique challenge that required extensive daily planning and coordination with subcontractors and airport management to work safely and protect facility personnel and the public from any potential dangers associated with the work. 

The project was completed in two phases – Phase 1 involved working on the northern exterior of the airport, while Phase 2 focused on the airport’s southern exterior. Phase 1 began in April 2015 and was completed in mid-December 2015 (lasting 31 weeks).  Phase 2 had a construction duration of 24 weeks and was completed in June 2016. Our team’s phasing plan and schedule resulted in completing the project three weeks earlier than anticipated.